Decision of the Žilina Regional Monuments Board on the planned restoration
The monuments board has set out everything that must precede the restoration of the manor house – from surveys through structural engineering to archaeology.

In March 2024 the owner of the manor house applied to the Regional Monuments Board in Žilina (KPÚ) for a decision on the planned restoration of the National Cultural Monument. At the end of May 2024 the Board delivered its decision. It has to be updated every year and attached to each grant application.
Conditions for carrying out the restoration
In brief:
- Arrange for preparatory documentation – an architectural-historical survey.
- Prepare project documentation – a remediation project to deal with the damp in the manor house.
- Prepare and submit to the Regional Monuments Board (KPÚ) for assessment a conservation survey evaluating the technical condition of the plaster layers and any paint layers inside and outside.
- Restoration of the façades may only take place after the heritage survey and the remediation project have been prepared and approved and the conservation survey has been carried out.
- Provide a digitised geodetic survey of the building.
- Arrange for a structural assessment.
- Submit to the Regional Monuments Board (KPÚ) the preparatory documentation – an architectural study for the restoration of the manor house that takes into account all conclusions of the approved heritage survey, the remediation project, the structural stabilisation project and the conservation proposal.
- Prepare the restoration project documentation at the level required for a building permit, including new electrical installations, lighting, heating, water connection, plumbing and other necessary professions.
- As the restoration requires intervention in the ground, an archaeological survey must be carried out before construction work begins.

What this means
Before any building work on the manor house can begin, a whole series of surveys, assessments and projects must be produced. It was precisely for the heritage surveys and preparatory documentation that the owner of the manor house applied for a grant from the Obnov si svoj dom programme in December 2024 and March 2026 – both applications were rejected due to lack of funds.
The first condition to be fulfilled will be the geodetic survey of the manor house, which is currently under way.